Wachovia Securities
Despite a significant change in deadline for completion, the project was finished on time and with success.
Houston, Texas
Size: 18,000 SF
Project Duration: 3 ½ months
Situation
Located
in approximately 22,000 SF in a high-rise office building in downtown
Houston, the Wachovia Securities’ office accommodated financial
professionals and administrative staff in a fairly typical office
environment. However, several factors – including an expiring lease and
a “renter’s market” – convinced the company to relocate to a smaller
leasehold on another floor of the same building.
During the
initial engagement, NWR Consulting Ltd. managed the design,
construction and relocation process, reducing time burdens on
Wachovia’s staff. However, soon after beginning the project in January
2004, we were informed that the deadline for completion was moved up to
mid-March – two and one-half months sooner than anticipated.
Value Statement
When
work began in January 2004, an expert team was quickly organized, all
assignments were communicated and a very aggressive schedule was
implemented that maximized activity compression techniques. Over the
course of the next several months:
• the design of the facility was completed,
• construction drawings were prepared and submitted for the building permit,
• construction was completed,
• the cable plant and security systems were installed, and
• furniture and personal effects were relocated.
Outcome
Constant
project management attention to the project enabled Wachovia to remain
focused on the normal challenges of its business. Moreover, the project
was delivered on schedule.