Aspen Manufacturing
NWR Discovery Process Leads to $1.7 million Savings
Houston, Texas
Size: 135,000 SF
Project Duration: 14 months
Situation
In
order to take advantage of expanding business opportunities, Aspen
Manufacturing, a maker of air conditioning parts and systems, wanted to
move its outdated, 180,000 SF facility to a new larger facility of
approximately 200,000 SF. The project was to be completed in a
built-to-suit arrangement in which Aspen Manufacturing would own the
facility upon completion. The engagement included management of the
entire process of design, construction, relocation and occupancy.
Value Statement
Working
directly and closely with Aspen, NWR Consulting first examined all
aspects of the company’s manufacturing processes, from the receipt of
materials to the shipping of the final product. We studied workflow,
material handling techniques procedures and employee culture. Once the
examination process was complete, we discovered that by reorganizing
Aspen’s manufacturing operations, the company could be housed
comfortably in a building of no more than 135,000 SF. Even at just
two-thirds the original, anticipated space, the new facility would
leave room for expansion beyond initial operational requirements.
Outcome
Because
of early analysis of Aspen’s operational requirements, the amount of
building to be constructed was dramatically reduced. This saved Aspen
approximately $1.7 million in project costs. In addition, the company
dramatically improved its manufacturing processes and materials
handling procedures. Finally, throughout the project, Aspen was able to
remain focused on the day-to-day challenges of their business without
sacrificing any resources for the facility project.